Paper Pattern of Test for the Post of E.E. (Trans), Dy E.E. (Trans/Civil) & Je (Trans)-Trainee 2015
Section
|
Number of Questions
|
Marks
|
Time
|
Test of Professional Knowledge
|
50
|
110
|
Composite time of 2
hours for all the
sections together
|
General Aptitude, Logical / Analytical
Reasoning, Problem Solving, etc.
|
80
|
40
|
|
Total
|
130
|
150
|
Professional Knowledge Test Syllabus for the Post of
Executive Engineer (Trans) & Dy. Executive Engineer (Trans)
- Survey, profiles, clearances, tower spotting, sag-tension, normal towers extensions, special towers, PTCC, Railway, Aviation, Forest & other statutory approval.
- Forces on towers, design criteria, F.O.S
- Choice of Conductor size & configuration, resistance, reactance, capacitance of lines & their impact on design & performance of lines
- Conductor / Earthwire hardware & accessories, Insulators, string efficiency, Tower Accessories
- Earthing –types, criteria, Ground wire
- Foundations of towers, stub-setting, Erection of towers, stringing
- Operation & Maintenance of lines (live line & dead line) monitoring performance parameters, trouble shooting, patrolling
- Testing, commissioning of lines
- Plans/targets of MAHATRANSCO, Power status of the state & the country
- Protective relaying systems.
- Choice of Voltage, requirement of land, acquisition process.
- Fault level, choice of rating of equipments & Busbars
- Earthing System – design & construction, illumination
- Control & relaying systems, control & power cabling.
- Various Bus-bar types & their choice, layout
- Ratings of Circuit breaker, CTs, PTs, CVTs, Las, etc
- Erection, commissioning, testing of power transformers, drying out transformer oil, fire fighting.
- Condition monitoring of equipment
- Management of EHV Projects.
- O&M of EHV Sub-Stations
- PLCC, Battery, Battery charging, auxiliary supply
- ABT metering, load dispatch, open access & other matters relating to transmission provided for Electricity Act-2003.
- Power System analysis studies.
- Commercial mechanism of grid operation.
- Regulatory requirements and commitment
Professional Knowledge
Test Syllabus for the Post of Dy. Executive Engineer (Civil)
EHV Transmission Lines:
- Survey, profiles, clearances, tower spotting, PTCC, Railway, Aviation, Forest & other statutory approvals.
- Forces on towers
- Foundations of towers, stub setting
- Land Acquisition- Procedures, Rules, Regulations & Acts, Land requirement.
- Soil Mechanics: Soil properties, soil investigation required for substation.
- Concrete Technology – Concrete mix design. Material Cement / Stand / Metal / Reinforcement.
- Reinforcement detailing – Reading of drawings, Bar bending Schedule etc.
- Construction Technology – Material consumption for different items, estimate preparation, Rate analysis, Specifications & mode of measurements. Rehabilitation of old structures, Repairs/water proofing etc.
- Bonds of brick masonry, stone masonry etc.
- Theory of Structures – Elementary knowledge Shear force/ Bending movement, Forces on structures like portal retaining wall, water tanks.
- Preliminary knowledge of water supply and Sanitary Engineering.
Professional
Knowledge Test Syllabus for the Post of Jr. Engineer (Trans) - Trainee
- Professional Knowledge Test will contain questions on Electrical Engineering/Power Engineering field which candidate have studied at the Degree level.